Edmonton Metro Line Northwest Light Rail Transit Extension

Edmonton, Alberta

underwayPublic TransitPTIS
Federal contribution
$97.2M
$97,200,000
Federal share40%

of $243.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 11, 2019
today
20192022202520282031
BuiltForecast
Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Edmonton
Construction start
May 28, 2020(actual)
Construction end
Dec 31, 2030(forecast)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2020