Mayo Water, Sewer and Road Upgrades – Phase 3, Area 3

Mayo, Yukon

completeWastewaterGIS
Federal contribution
$6.5M
$6,513,750
Federal share75%

of $8.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 2, 2019
20202021202220232024
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Mayo
Construction start
Jul 20, 2020(actual)
Construction end
Oct 1, 2024(actual)

Against the original forecast

  • Construction start2 months lateforecast May 15, 2020
  • Construction end13 months earlyforecast Oct 31, 2025