Stewart-Keno Transmission Line Rehabilitation
Federal contribution
$21.7M
$21,712,280
Federal share75%
of $28.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 5, 2019
20202021
Built
Approved 6 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Yukon Energy Corporation
- Construction start
- Sep 30, 2019(actual)
- Construction end
- Oct 28, 2021(actual)
Against the original forecast
- Construction start5 months earlyforecast Mar 2, 2020
- Construction end5 months earlyforecast Mar 17, 2022