Culvert Replacement on Chisasibi Road

Chisasibi, Quebec

completeHighways and RoadsRNIS
Federal contribution
$2.9M
$2,884,450
Federal share50%

of $5.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 19, 2020
202020212022
Built

Approved 10 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jun 18, 2020(actual)
Construction end
Feb 15, 2022(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jun 2, 2020
  • Construction end7 weeks lateforecast Dec 31, 2021