Upgrades to the ventilation systems in the clinical spaces, emergency examination rooms as well as dental examination rooms
Federal contribution
$109,673
Federal share100%
of $109.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
202220232024
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Conseil cri de la santé et services sociaux de la Baie-James
- Construction start
- Jun 1, 2021(actual)
- Construction end
- Nov 29, 2023(actual)
Also in Chisasibi