Whitehorse South West Fire Risk Reduction

Whitehorse, Yukon

completeDisaster MitigationGIS
Federal contribution
$1.2M
$1,162,500
Federal share70%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 3, 2020
202020212022202320242025
Built

Approved 6 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Government of Yukon
Construction start
Oct 10, 2020(actual)
Construction end
Apr 1, 2025(actual)

Against the original forecast

  • Construction end9 months earlyforecast Dec 31, 2025