Water And Sewer Installation and Lift Station Upgrades - Englee
Englee, Newfoundland and Labrador
Federal contribution
$201,656
Federal share33%
of $604.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
202020212022
Built
Approved 3 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Englee
- Construction start
- Oct 12, 2021(actual)
- Construction end
- Jul 13, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 1, 2021
- Construction end7 months lateforecast Nov 30, 2021