Schedule

Announced and approvedJul 7, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Englee
Construction start
Sep 25, 2017(actual)
Construction end
Aug 21, 2018(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Aug 1, 2017
  • Construction end7 months earlyforecast Mar 31, 2019