French Island Water System Upgrades
Englee, Newfoundland and Labrador
Federal contribution
$268,132
Federal share50%
of $536.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Englee
- Construction start
- Sep 25, 2017(actual)
- Construction end
- Aug 21, 2018(actual)
Against the original forecast
- Construction start8 weeks lateforecast Aug 1, 2017
- Construction end7 months earlyforecast Mar 31, 2019
Also in Englee
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47065 in the federal list. How to read these figures.