Back to projects

Soccer Field Upgrade

Holyrood, Newfoundland and Labrador

completeRecreationCCRIS
Federal contribution
$217,024
Federal share33%

of $652.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
202020212022
Built

Approved 3 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Town of Holyrood
Construction start
Jun 4, 2021(actual)
Construction end
Jul 28, 2022(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 1, 2021
  • Construction end7 months lateforecast Dec 31, 2021

Also in Holyrood

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53855 in the federal list. How to read these figures.