Soccer Field Upgrade
Holyrood, Newfoundland and Labrador
Federal contribution
$217,024
Federal share33%
of $652.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
202020212022
Built
Approved 3 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Holyrood
- Construction start
- Jun 4, 2021(actual)
- Construction end
- Jul 28, 2022(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 1, 2021
- Construction end7 months lateforecast Dec 31, 2021
Also in Holyrood
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53855 in the federal list. How to read these figures.