Marine Drive Bridge Replacement

Old Perlican, Newfoundland and Labrador

completeHighways and RoadsRNIS
Federal contribution
$112,183
Federal share33%

of $336.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
2020
Built

Approved 7 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Old Perlican
Construction start
Nov 25, 2019(actual)
Construction end
Jul 24, 2020(actual)

Against the original forecast

  • Construction start4 months earlyforecast Apr 1, 2020
  • Construction end3 months earlyforecast Oct 31, 2020

Also in Old Perlican

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53887 in the federal list. How to read these figures.