Marine Drive Bridge Replacement
Old Perlican, Newfoundland and Labrador
Federal contribution
$112,183
Federal share33%
of $336.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
2020
Built
Approved 7 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Old Perlican
- Construction start
- Nov 25, 2019(actual)
- Construction end
- Jul 24, 2020(actual)
Against the original forecast
- Construction start4 months earlyforecast Apr 1, 2020
- Construction end3 months earlyforecast Oct 31, 2020
Also in Old Perlican
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53887 in the federal list. How to read these figures.