Water Pressure Booster Pump Upgrade
Old Perlican, Newfoundland and Labrador
Federal contribution
$141,366
Federal share50%
of $282.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Old Perlican
- Construction start
- Oct 2, 2017(actual)
- Construction end
- Mar 31, 2018(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 30, 2017
- Construction end6 months lateforecast Sep 30, 2017
Also in Old Perlican
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46977 in the federal list. How to read these figures.