Upgrades to the Pumping System and Storage Tank in the Town of Small Point-Adam's Cove-Blackhead-Broad Cove
Small Point-Adam's Cove-Blackhead-, Newfoundland and Labrador
Federal contribution
$44,771
Federal share40%
of $112.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
202020212022
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Small Point-Adams Cove-Blackhead-Broad Cove
- Construction start
- Oct 29, 2020(actual)
- Construction end
- Dec 22, 2021(actual)
Against the original forecast
- Construction start5 months lateforecast Jun 1, 2020
- Construction end3 months earlyforecast Mar 31, 2022
Also in Small Point-Adam's Cove-Blackhead-
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53907 in the federal list. How to read these figures.