Upgrade Well Houses
Small Point-Adam's Cove-Blackhead-, Newfoundland and Labrador
Federal contribution
$53,825
Federal share40%
of $134.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
20242025
Built
Approved 18 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Small Point-Adams Cove-Blackhead-Broad Cove
- Construction start
- Apr 22, 2025(actual)
- Construction end
- May 30, 2025(actual)
Against the original forecast
- Construction start4 weeks earlyforecast May 18, 2025
- Construction end7 weeks earlyforecast Jul 21, 2025