Drainage Upgrades in Chipp's Hill Area Town of Middle Arm
Middle Arm, Newfoundland and Labrador
Federal contribution
$64,972
Federal share40%
of $162.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
20202021
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Middle Arm
- Construction start
- Nov 19, 2020(actual)
- Construction end
- Aug 5, 2021(actual)
Against the original forecast
- Construction start8 weeks earlyforecast Jan 15, 2021
- Construction end5 weeks lateforecast Jul 1, 2021