New Chlorination System, Booster Pumps and Filter
Middle Arm, Newfoundland and Labrador
Federal contribution
$278,450
Federal share40%
of $696.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 28, 2022
2022202320242025
Built
Approved 2 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Middle Arm
- Construction start
- Aug 26, 2024(actual)
- Construction end
- May 21, 2025(actual)
Against the original forecast
- Construction start4 months lateforecast May 7, 2024
- Construction end6 months lateforecast Nov 28, 2024
Also in Middle Arm
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61178 in the federal list. How to read these figures.