Back to projects

New Chlorination System, Booster Pumps and Filter

Middle Arm, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$278,450
Federal share40%

of $696.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 28, 2022
2022202320242025
Built

Approved 2 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Middle Arm
Construction start
Aug 26, 2024(actual)
Construction end
May 21, 2025(actual)

Against the original forecast

  • Construction start4 months lateforecast May 7, 2024
  • Construction end6 months lateforecast Nov 28, 2024