Lift Station Upgrades - Gambo

Gambo, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$124,251
Federal share37%

of $335.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 30, 2019
20202021
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Gambo
Construction start
May 15, 2021(actual)
Construction end
Jun 20, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast Feb 1, 2021
  • Construction end3 months lateforecast Mar 31, 2021