Parker's Cove - Water Treatment System

Parker's Cove, Newfoundland and Labrador

completeDrinking WaterRNIS
Federal contribution
$188,058
Federal share40%

of $470.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021202220232024
Built

Approved 3 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Parker's Cove
Construction start
May 6, 2024(actual)
Construction end
Oct 10, 2024(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jun 1, 2024
  • Construction end9 months earlyforecast Jun 30, 2025

Also in Parker's Cove

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53944 in the federal list. How to read these figures.