Back to projects

Sewer Main Replacement

Parker's Cove, Newfoundland and Labrador

completeWastewaterCWWF
Federal contribution
$175,222
Federal share47%

of $370.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Parker's Cove
Construction start
Sep 5, 2017(actual)
Construction end
Oct 31, 2017(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 24, 2017
  • Construction end2 months lateforecast Aug 28, 2017

Also in Parker's Cove

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47058 in the federal list. How to read these figures.