Pump House Upgrades - Roddickton-Bide Arm
Roddickton-Bide Arm, Newfoundland and Labrador
Federal contribution
$74,278
Federal share40%
of $187.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
20202021
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Roddickton-Bide Arm
- Construction start
- Aug 24, 2020(actual)
- Construction end
- Jan 31, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast May 30, 2020
- Construction end8 weeks earlyforecast Mar 31, 2021