Sewage Holding Tank - Town of Roddickton-Bide Arm
Roddickton-Bide Arm, Newfoundland and Labrador
Federal contribution
$210,751
Federal share40%
of $526.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 15, 2021
20212022
Built
Approved 7 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Roddickton-Bide Arm
- Construction start
- Sep 27, 2021(actual)
- Construction end
- Oct 14, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast May 30, 2021
- Construction end6 months earlyforecast Mar 31, 2023
Also in Roddickton-Bide Arm
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56886 in the federal list. How to read these figures.