Sewage Holding Tank - Town of Roddickton-Bide Arm

Roddickton-Bide Arm, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$210,751
Federal share40%

of $526.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 15, 2021
20212022
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Roddickton-Bide Arm
Construction start
Sep 27, 2021(actual)
Construction end
Oct 14, 2022(actual)

Against the original forecast

  • Construction start4 months lateforecast May 30, 2021
  • Construction end6 months earlyforecast Mar 31, 2023

Also in Roddickton-Bide Arm

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56886 in the federal list. How to read these figures.