Water and Sewer Capital Works 2018-2019

Salmon Cove, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$276,880
Federal share40%

of $692.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
2020
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Salmon Cove
Construction start
Jun 9, 2020(actual)
Construction end
Sep 30, 2020(actual)

Against the original forecast

  • Construction end2 months earlyforecast Dec 15, 2020

Also in Salmon Cove

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53958 in the federal list. How to read these figures.