Sewer Pumping Station Upgrade - 2020 Capital Works
Salmon Cove, Newfoundland and Labrador
Federal contribution
$84,066
Federal share40%
of $210.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 15, 2021
20212022
Built
Approved 8 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Salmon Cove
- Construction start
- Oct 21, 2021(actual)
- Construction end
- Aug 11, 2022(actual)
Against the original forecast
- Construction start5 months lateforecast May 20, 2021
- Construction end8 months lateforecast Dec 14, 2021
Also in Salmon Cove
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56861 in the federal list. How to read these figures.