Highroad South Water and Sewer - Carbonear

Carbonear, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$268,227
Federal share40%

of $670.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
202020212022
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Carbonear
Construction start
Jun 23, 2021(actual)
Construction end
Jun 7, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 15, 2021
  • Construction end3 weeks earlyforecast Jun 30, 2022