Lift Station Upgrades Phase 2 - Centreville-Wareham-Trinity
Centreville-Wareham-Trinity, Newfoundland and Labrador
Federal contribution
$50,160
Federal share30%
of $165.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
20202021
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Centreville-Wareham-Trinity
- Construction start
- Apr 1, 2021(actual)
- Construction end
- Sep 5, 2021(actual)
Against the original forecast
- Construction start6 weeks lateforecast Feb 15, 2021
- Construction end7 months earlyforecast Mar 31, 2022
Also in Centreville-Wareham-Trinity