Back to projects

New Forcemain Upgrades

Centreville-Wareham-Trinity, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$172,852
Federal share40%

of $432.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 28, 2022
2022202320242025
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Jun 3, 2025(actual)
Construction end
Aug 18, 2025(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 15, 2025
  • Construction end3 weeks lateforecast Jul 30, 2025

Also in Centreville-Wareham-Trinity

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62227 in the federal list. How to read these figures.