New Forcemain Upgrades
Centreville-Wareham-Trinity, Newfoundland and Labrador
Federal contribution
$172,852
Federal share40%
of $432.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 28, 2022
2022202320242025
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Centreville-Wareham-Trinity
- Construction start
- Jun 3, 2025(actual)
- Construction end
- Aug 18, 2025(actual)
Against the original forecast
- Construction start3 weeks lateforecast May 15, 2025
- Construction end3 weeks lateforecast Jul 30, 2025
Also in Centreville-Wareham-Trinity
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62227 in the federal list. How to read these figures.