Water Distribution System Upgrades - Highlands

Bay St. George South, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$78,292
Federal share40%

of $195.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
2020
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Jul 14, 2020(actual)
Construction end
Sep 30, 2020(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 30, 2020
  • Construction end4 weeks lateforecast Aug 30, 2020

Also in Bay St. George South

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53997 in the federal list. How to read these figures.