Water Distribution System Upgrades - Highlands
Bay St. George South, Newfoundland and Labrador
Federal contribution
$78,292
Federal share40%
of $195.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
2020
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Local Service District of Bay St. George South
- Construction start
- Jul 14, 2020(actual)
- Construction end
- Sep 30, 2020(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 30, 2020
- Construction end4 weeks lateforecast Aug 30, 2020