Improvements to Community Playground (McKay's)
Bay St. George South, Newfoundland and Labrador
Federal contribution
$14,705
Federal share29%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 16, 2020
202120222023
Built
Approved 3 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Local Service District of Bay St. George South
- Construction start
- Sep 1, 2023(actual)
- Construction end
- Oct 5, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2023
- Construction end3 months lateforecast Jul 1, 2023
Also in Bay St. George South
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56962 in the federal list. How to read these figures.