Reconstruction of Beaver Lake Road
Federal contribution
$755,355
Federal share50%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2019
2020
Built
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Municipality of Trent Lakes
- Construction start
- Jun 1, 2020(actual)
- Construction end
- Oct 31, 2020(actual)
Also in Trent Lakes
- Replacement of the Existing Standby Generator at Buckhorn Lake Estates$20.6K
- Replacement of Existing Highlift Pumps (2) at Buckhorn Lake Estates$13.0K
- Addition of standby filter cartridge housing for Alpine Water treatment plant$3.8K
- Installation of Two (2) sample hydrants and One (1) Flushing hydrant at Buckhorn Lake Estates$2.6K
- Replacement of Well Pump #1 Buckhorn Lake Estates$1.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54096 in the federal list. How to read these figures.