Back to projects

Replacement of Existing Highlift Pumps (2) at Buckhorn Lake Estates

Trent Lakes, Ontario

completeDrinking WaterCWWF
Federal contribution
$13,000
Federal share50%

of $26.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Trent Lakes
Construction start
Jan 1, 2018(actual)
Construction end
Aug 12, 2019(actual)

Against the original forecast

  • Construction start6 months lateforecast Jul 1, 2017
  • Construction end16 months lateforecast Mar 31, 2018

Also in Trent Lakes

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49984 in the federal list. How to read these figures.