Norman Wells Roadway and Drainage Improvements
Norman Wells, Northwest Territories
Federal contribution
$1.1M
$1,125,000
Federal share66%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2019
20202021
Built
Approved 3 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Norman Wells
- Construction start
- Aug 10, 2020(actual)
- Construction end
- Apr 30, 2021(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 15, 2020
- Construction end2 months earlyforecast Jul 10, 2021
Also in Norman Wells
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54105 in the federal list. How to read these figures.