Back to projects

Bay Island Bridge Study and Design

Behchokö (Rae-Edzo), Northwest Territories

underwayHighways and RoadsRNIS
Federal contribution
$262,500
Federal share75%

of $350.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 23, 2021
today
202220232024202520262027
BuiltForecast

Approved 2 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jun 1, 2023(actual)
Construction end
Nov 30, 2026(forecast)

Against the original forecast

  • Construction start12 months earlyforecast Jun 1, 2024