Montrose Wastewater Treatment Plant Upgrades
Federal contribution
$1.0M
$1,003,105
Federal share40%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 27, 2019
202020212022202320242025
Built
Approved 5 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Montrose
- Construction start
- Mar 25, 2022(actual)
- Construction end
- Feb 3, 2025(actual)
Against the original forecast
- Construction start4 months lateforecast Nov 30, 2021
- Construction end7 weeks lateforecast Dec 13, 2024
Also in Montrose
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54119 in the federal list. How to read these figures.