Montrose Wastewater Treatment Plant Upgrades

Montrose, British Columbia

completeWastewaterCWWF
Federal contribution
$395,000
Federal share50%

of $790.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 30, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Montrose
Construction start
May 29, 2017(actual)
Construction end
Oct 6, 2017(actual)

Against the original forecast

  • Construction start5 months earlyforecast Oct 15, 2017
  • Construction end4 months earlyforecast Feb 10, 2018

Also in Montrose

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47691 in the federal list. How to read these figures.