McMeekan Causeway Stabilization
Yellowknife, Northwest Territories
Federal contribution
$217,521
Federal share75%
of $290.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2019
2020202120222023
Built
Approved 4 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- City of Yellowknife
- Construction start
- Jul 1, 2020(actual)
- Construction end
- Nov 30, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2020
- Construction end4.3 years earlyforecast Mar 31, 2027