Back to projects

Yellowknife Paving

Yellowknife, Northwest Territories

completeHighways and RoadsRNIS
Federal contribution
$2.8M
$2,756,250
Federal share72%

of $3.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2019
2020202120222023
Built

Approved 4 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
City of Yellowknife
Construction start
Jul 16, 2019(actual)
Construction end
Feb 8, 2023(actual)

Against the original forecast

  • Construction end4 months lateforecast Oct 1, 2022

Also in Yellowknife

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54125 in the federal list. How to read these figures.