Yellowknife - Waste Diversion, Reduction and Community Composting
Yellowknife, Northwest Territories
Federal contribution
$1.7M
$1,725,000
Federal share75%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 31, 2019
today
2020202220242026
BuiltForecast
Approved 2 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Yellowknife
- Construction start
- Jul 1, 2020(actual)
- Construction end
- Mar 31, 2027(forecast)
Against the original forecast
- Construction start7 weeks lateforecast May 15, 2020
Also in Yellowknife