Reconstruction of Durham Street and Brock Street

Stone Mills, Ontario

completeHighways and RoadsRNIS
Federal contribution
$441,504
Federal share50%

of $883.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 29, 2019
2020
Built
Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Township of Stone Mills
Construction start
Sep 14, 2020(actual)
Construction end
Nov 10, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2020