Reconstruction of Durham Street and Brock Street
Federal contribution
$441,504
Federal share50%
of $883.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 29, 2019
2020
Built
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Township of Stone Mills
- Construction start
- Sep 14, 2020(actual)
- Construction end
- Nov 10, 2020(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2020
Also in Stone Mills