Arena Floor Replacement For Stone Mills Recreation Centre
Federal contribution
$400,000
Federal share40%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2021
20212022
Built
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Township of Stone Mills
- Construction start
- Mar 30, 2022(actual)
- Construction end
- Nov 30, 2022(actual)
Against the original forecast
- Construction end2 months lateforecast Sep 30, 2022
Also in Stone Mills
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57646 in the federal list. How to read these figures.