Murphy's Bridge Replacement

Kerns, Ontario

completeHighways and RoadsRNIS
Federal contribution
$276,986
Federal share60%

of $461.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 20, 2019
20202021
Built

Approved 4 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Township of Kerns
Construction start
Oct 26, 2020(actual)
Construction end
Dec 16, 2020(actual)

Against the original forecast

  • Construction start14 months lateforecast Aug 12, 2019
  • Construction end2 weeks earlyforecast Dec 31, 2020

Also in Kerns

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54202 in the federal list. How to read these figures.