Murphy's Bridge Replacement
Federal contribution
$276,986
Federal share60%
of $461.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 20, 2019
20202021
Built
Approved 4 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Township of Kerns
- Construction start
- Oct 26, 2020(actual)
- Construction end
- Dec 16, 2020(actual)
Against the original forecast
- Construction start14 months lateforecast Aug 12, 2019
- Construction end2 weeks earlyforecast Dec 31, 2020