Back to projects

Rehabilitation of Public Facilities

Kerns, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
202220232024
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of Kerns
Construction start
Jun 1, 2021(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction end12 months earlyforecast Dec 31, 2024

Also in Kerns

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59566 in the federal list. How to read these figures.