Rehabilitation of Weslemkoon Lake Road - Phase 2
Federal contribution
$1.2M
$1,194,030
Federal share60%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 1, 2019
20202021
Built
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Township of Tudor and Cashel
- Construction start
- Mar 9, 2020(actual)
- Construction end
- Nov 4, 2021(actual)
Against the original forecast
- Construction end7 months earlyforecast Jun 1, 2022