Rehabilitation of Millbridge Roads Garage

Tudor and Cashel, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$26,671
Federal share80%

of $33.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
20222023
Built

Approved 6 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 1, 2021(actual)
Construction end
Mar 31, 2023(actual)

Against the original forecast

  • Construction end7 months lateforecast Aug 15, 2022

Also in Tudor and Cashel

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60175 in the federal list. How to read these figures.