Hawk Lake Road Bridge Replacement
Federal contribution
$462,553
Federal share50%
of $925.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2019
2020
Built
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- The County of Haliburton
- Construction start
- Jul 8, 2020(actual)
- Construction end
- Oct 23, 2020(actual)
Against the original forecast
- Construction start6 months lateforecast Jan 1, 2020
- Construction end2 months earlyforecast Dec 31, 2020
Also in Haliburton