Upgrading of the Haliburton County Rail Trail Corridor
Federal contribution
$107,250
Federal share40%
of $268.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 29, 2021
202220232024
Built
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- The County of Haliburton
- Construction start
- Sep 28, 2021(actual)
- Construction end
- Aug 29, 2024(actual)
Against the original forecast
- Construction start4 weeks lateforecast Sep 1, 2021
- Construction end16 months earlyforecast Dec 31, 2025
Also in Haliburton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57578 in the federal list. How to read these figures.