Municipality of the District of Argyle - Wedgeport Wastewater Improvements Phase 3

Argyle, Nova Scotia

completeWastewaterGIS
Federal contribution
$417,144
Federal share40%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 2, 2019
20202021202220232024
Built

Approved 2 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Sep 22, 2023(actual)
Construction end
Nov 30, 2023(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 17, 2023
  • Construction end4 weeks earlyforecast Dec 29, 2023