Wedgeport wastewater project - phase 2 of 3

Argyle, Nova Scotia

completeWastewaterCWWF
Federal contribution
$429,007
Federal share50%

of $858.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Oct 2, 2017(actual)
Construction end
Feb 5, 2019(actual)

Against the original forecast

  • Construction end8 weeks earlyforecast Mar 31, 2019

Also in Argyle

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47205 in the federal list. How to read these figures.