Pat and the Elephant Van Replacement
Charlottetown, Prince Edward Island
Federal contribution
$169,297
Federal share39%
of $437.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 12, 2019
20202021202220232024
Built
Approved 8 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Pat and the Elephant
- Construction start
- Oct 17, 2019(actual)
- Construction end
- Feb 16, 2024(actual)
Against the original forecast
- Construction start7 weeks lateforecast Sep 1, 2019
- Construction end6 weeks earlyforecast Mar 31, 2024
Also in Charlottetown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54320 in the federal list. How to read these figures.