Water Treatment Upgrade

Wells, British Columbia

completeDrinking WaterSCF
Federal contribution
$213,286
Federal share33%

of $639.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 27, 2019
2020202220242026
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
District of Wells
Construction start
Nov 14, 2023(actual)
Construction end
Nov 13, 2025(actual)

Against the original forecast

  • Construction start3 months earlyforecast Feb 1, 2024
  • Construction end5 months earlyforecast Mar 31, 2026