Water Treatment Upgrade
Federal contribution
$213,286
Federal share33%
of $639.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 27, 2019
2020202220242026
Built
Approved 2 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- District of Wells
- Construction start
- Nov 14, 2023(actual)
- Construction end
- Nov 13, 2025(actual)
Against the original forecast
- Construction start3 months earlyforecast Feb 1, 2024
- Construction end5 months earlyforecast Mar 31, 2026
Also in Wells
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54336 in the federal list. How to read these figures.