Water and Sewage Infrastructure

Wells, British Columbia

completeDrinking WaterCWWF
Federal contribution
$175,000
Federal share50%

of $350.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
District of Wells
Construction start
Sep 3, 2018(actual)
Construction end
Sep 6, 2019(actual)

Against the original forecast

  • Construction start17 months lateforecast Apr 3, 2017
  • Construction end7 months earlyforecast Mar 31, 2020

Also in Wells

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49832 in the federal list. How to read these figures.