Stratford Sewer Lift Station Upgrades - Pondside/Bayside/Corish

Stratford, Prince Edward Island

completeWastewaterGIS
Federal contribution
$917,708
Federal share36%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 23, 2019
202020212022202320242025
Built

Approved 5 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Stratford
Construction start
Jul 31, 2022(actual)
Construction end
Sep 30, 2025(actual)

Against the original forecast

  • Construction end2 months lateforecast Jul 31, 2025